City Street Updates

Active/Upcoming Road Rehabilitation Projects

*Schedules may change to accommodate weather conditions or other unforeseen factors. 

Wood St & Northington St: July 16 - September

UPDATE 6.11.2025: Due to weather conditions, the planned road closures on Wood St. have been postponed until Monday, June 16, 2025. We’ll share an updated schedule as soon as that information becomes available. Thank you for your patience and understanding

June 4, 2025- Beginning Thursday, June 12, road construction will begin on Wood Street and Northington Street to improve drainage, add curb and gutter, and provide new pavement. The project is expected to be completed by September 3 and will be carried out in phases. Each affected resident should have received a door hanger notice with specific details about the construction timeline for their area. Please see attachment below for Wood St & Northington St Road Closure for maps. 

DETOUR & PARKING NOTICE:
• Street parking will not be allowed on the affected streets during construction.
• Residents will need to park on adjacent side streets during construction phases.
• Detour signs will be posted to help guide residents around the work zones.
• Emergency vehicle access will be maintained at all times.

Phase Schedule (maps attached):
Phase 1: Wood St. (Dougherty Creek to 963)- June 12 – July 12
Phase 2: Wood St. (Brier St. to Kerr St.)- June 12 – July 12
Phase 3: Wood St. (SH-29 to Brier St.)- July 14 – August 15
Phase 5: Northington St. (Rhomberg to Wallace Riddell Parking Lot)- July 14 – August 15
Phase 6: Northington St. (Hill St. to Wallace Riddell Parking Lot)- August 16 – September 3
Phase 7: Wood St. (Kerr St. to Dougherty Creek)- July 14 – August 15 (Open to traffic but under construction)
For questions, please email the contractor at zach@gageandcadeconstruction.com or contact the City of Burnet at 512-756-2402

Houston Clinton  Drive Closure: March 27 - May

UPDATE 6.6.2025
Change of plans — paving will now take place tomorrow, Saturday.
Flaggers will be on-site to assist with traffic—thank you in advance for your cooperation and patience.

UPDATE 6.4.2025
Great news! The contractor has made solid progress, and we're finally seeing the light at the end of the tunnel.
Weather permitting, final paving is scheduled for this Friday, including:

  • Paving the eastbound lane
  • Applying a second layer of asphalt to the westbound lane

In the meantime, crews are still hard at work on cleanup, curbs, and sidewalks. Please continue to drive with caution and stay alert for any changes in traffic patterns. We’re almost there—thank you for your patience!

Original Post March 14, 2025- The first portion of Houston Clinton at SH-281 will be closed for demolition. This closure will require traffic to be rerouted through Cary Johnson Parkway. Please see attachment below for Houston Clinton Road Closure for more information.

 

This map displays all the streets that have been maintained over the past three years (since 2022), along with their current roadway conditions. It also provides a glimpse of the tentative schedule for upcoming road repairs. For more detailed information on upcoming road repairs please see information below the map. If there are active projects underway, you can find more detailed information about those repairs in the section located beneath the map.